Q. 29 Demand during lead time with associated probabilities is shown below:

Gate ME 2014-4 Question Paper With Solutions
Expected demand during lead time is _____.

Answer: (74.55)

Explanation:

Gate ME 2014-4 Question Paper With Solutions