Q. 60 Consider the given project network, where numbers along various activities
represent the normal time. The free float on activity 4-6 and the project duration,
respectively, are
(A) 2, 13
(B) 0, 13
(C) -2, 13
(D) 2, 12
Answer: (A)
Explanation: