Q. 60 A project has four activities P, Q, R and S as shown below.
The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/-
per day. If the project duration has to be crashed down to 9 days, the total cost
(in Rupees) of the project is ______
Answer: (12400)
Explanation: