Gate Solved Gate ME-2012 Question Paper With Solutions Facebook WhatsApp Twitter Pinterest Email Q 54. The critical path for the project is (A) a – b – e – g – h (B) a – c – g – h (C) a – d – f – h (D) a – b – c – f – h Answer: (C ) Explanation: Learn More: Gate ME-2016-3 Question Paper With Solutions