Q 54. The critical path for the project is
(A) a – b – e – g – h
(B) a – c – g – h
(C) a – d – f – h
(D) a – b – c – f – h
Answer: (C )
Explanation:
Q 54. The critical path for the project is
(A) a – b – e – g – h
(B) a – c – g – h
(C) a – d – f – h
(D) a – b – c – f – h
Answer: (C )
Explanation: