Gate ME-2012 Question Paper With Solutions

Q 13.  Which one of the following is NOT a decision taken during the aggregate
production planning stage ?

(A) Scheduling of machines

(B) Amount of labour to be committed

(C) Rate at which production should happen

(D) Inventory to be carried forward

Answer: (A)

Explanation:

Gate ME-2012 Question Paper With Solutions

Learn More:   Gate EE-2006 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here