Q 84.
The expected completion time of the project is:
(A) 238 days
(B) 224 days
(C) 171 days
(D) 155 days
Answer: (D)
Explanation:
Q 84.
The expected completion time of the project is:
(A) 238 days
(B) 224 days
(C) 171 days
(D) 155 days
Answer: (D)
Explanation: