Gate ME-2006 Question Paper With Solutions

Q 20. In an MRP system, component demand is:

(A) forecasted

(B) established by the master production schedule

(C) calculated by the MRP system from the master production schedule

(D) ignored

Answer: (C)

Explanation:

Gate ME-2006 Question Paper With Solutions

Learn More:   Gate EC-2020 Question Paper With Solutions

LEAVE A REPLY

Please enter your comment!
Please enter your name here