Q.39. Determine the correctness or otherwise of the following Assertion (A) and the Reason (R).Assertion :Fast decoupled load flow method gives approximate load flow solutionbecause it uses several assumptions.Reason :Accuracy depends on the power mismatch vector tolerance.

(A)Both (A) and (R) are true and (R) is the correct reason for (A).
(B)Both (A) and (R) are true and (R) is not the correct reason for (A).
(C)Both (A) and (R) are false.
(D) (A) is false and (R) is true
Answer:(A)
Explanation:
Gate EE-2015-1 Question Paper With Solutions Gate EE-2015-1 Question Paper With Solutions