Gate EE-2014-1 Question Paper With Solutions

Q. 53 The over current relays for the line protection and loads connected at the buses
are shown in the figure.

Gate EE-2014-1 Question Paper With Solutions
The relays are IDMT in nature having the characteristic

Gate EE-2014-1 Question Paper With Solutions

The maximum and minimum fault currents at bus B are 2000 A and 500 A
respectively. Assuming the time multiplier setting and plug setting for relay Gate EE-2014-1 Question Paper With Solutions
to be 0.1 and 5 A respectively, the operating time of RB (in seconds) is_____.

Answer:(0.226)

Explanation:

Gate EE-2014-1 Question Paper With Solutions Gate EE-2014-1 Question Paper With Solutions

Learn More:   Gate EE-2003 Question Paper With Solutions