Q. 32 A load center of 120 MW derives power from two power stations connected by
220 kV transmission lines of 25 km and 75 km as shown in the figure below. The
three generators are of 100 MW capacity each and have identical
fuel cost characteristics. The minimum loss generation schedule for supplying the
120 MW load is
Answer:(A)
Explanation: