Q. 10 The following are the starting and ending times of cetivities A, B, C, D, E, F, G and H    respectively in chronological order;”as bs aa ae ds ae es fs be de gs ee fehsgehelHere, xs denotes the starting time and xe  denotes  the ending  time of  activity X . need to schedule the activities in a set of rooms available to us. An activity can be scheduled in a room only if the room is reserved for the activity for its entire duration. What is the minimum number of rooms required?

(A) 3

(B) 4

(C) 5

(D) 6

Answer: (B)

Explanation: