Domestic Per unit Rate:
As per this, for 1 to 25 units you have to pay ₹ 5.18, for next 35 units you have to pay ₹ 5.69, for 61 to 100 units the charges will be ₹6.7/-, for the units from 101 to 150 units the charges will be ₹7.45, for 151 to 300 units the per unit charges will be ₹7.62 and above 301 units the charges will be ₹9.21.
Also the consumer shall pay 15 per kW per month.
Additionally the consumer shall pay ₹ 15 as meter rent and ₹ 0.29 per unit as Monthly variable Cost. Government duty charges of 10%. See the below old bill example.
From | To | Per unit | Connected Load |
1 | 25 | 5.18 | 15/kW/Month |
25 | 60 | 5.69 | |
61 | 100 | 6.7 | |
101 | 150 | 7.45 | |
151 | 300 | 7.62 | |
301 | above | 9.21 |
HT Domestic:
The HT domestic consumer shall pay 7.42 for the summer, 7.39 for the monsoon and 7.36 for the winter season.
Commercial Tariff:
CESC Commercial consumer shall pay 6.57 per unit for their first 60 units, 7.24 for the next 40 units, ₹7.93 for the next 50 units from 101 to 150, for the 151 to 300 units the charges will be ₹8.49 and ₹9.26 per unit for the consumption of above 300 units.
From | To | Per unit | Connected Load |
1 | 60 | 6.57 | 24/kW |
61 | 100 | 7.24 | |
101 | 150 | 7.93 | |
151 | 300 | 8.49 | |
301 | above | 9.26 |
Government School, Government aided School or Government Sponsored School:
All units will be 5.24 per units
Cottage Industry / Artisan / Weavers / Small production oriented establishment not run by electricity as motive power:
Poultry, Duckery, Horticulture, Tissue culture, Floriculture, Herbal – Medicinal – Bio-diesel Plant Farming, Food Processing Unit:
Industries (Urban) Per unit Rate:
From | TO | Fixed Charges |
1 | 500 | 50/kW |
501 | 2000 | |
2000 | 3500 | |
>3500 |
CESC Bill Calculation:
Let us calculate the electricity bill for 500 units as per CESC Latest Tariff Order.
CESC Bill calclation For 500 units with 2kW Demand | ||||
From | To | Per unit | Units | Charges |
1 | 25 | 5.18 | 25 | 129.5 |
25 | 60 | 5.69 | 35 | 199.15 |
61 | 100 | 6.7 | 40 | 268 |
101 | 150 | 7.45 | 50 | 372.5 |
151 | 200 | 7.62 | 50 | 381 |
201 | 300 | 7.62 | 100 | 762 |
301 | above | 9.21 | 200 | 1842 |
Fixed Charges | 30 | |||
MVCA | 145 | |||
Duty | 412.915 | |||
Meter Rent | 15 | |||
Electricity Charges | 4557.065 |